The Jones Project


    In this project the home owner wanted to remove the existing hardwood floor in the foyer and carpet in the adjoining hall to lay tile. Day 1 consisted of removing the hardwood and glue that held it in place. Along with minor prep work on some small cracks. Now we can set tile in the foyer. This is Day 2 January 22, 2004

    We found a few large cracks in the slab and these had to be covered with special crack isolation membrane. This is Day 3 January 23, 2004

   

We also installed a Storm Door to the entrance.

 

Day 4 January 26, 2004 we finished laying tile. Ready for grout.

  

All finished